PECO PROJECTS IN THE TOWNSHIP

PECO is performing work in Huntingdon Pike and Byberry Road
Posted on 08/31/2026
ROAD RESTRICTIONS: BYBERRY RD AND HUNTINGDON PKPECO is performing work on Huntingdon Pike and Byberry road. Please allow for extra travel time through these areas.


Huntingdon Pike from Red Lion Road to Alden Road 
Updated 8/31/26
All of Huntingdon Pike (from Red Lion to Alden) will now be completed at night Monday- Thursday 10 pm to 6 am (no work on Labor Day).  This will begin Monday, Aug. 31, 2026.

Updated 8/10/26:
This project's tentative start date is 8/17
PECO will be installing 2,000 ft of gas main.
Traffic control operations are in place with flaggers maintaining a one-lane roadway.  Local and emergency traffic will have access. Between Red Lion Road and Buck Road will be completed during night hours 8pm-5am Monday-Thursday. From Buck Road to Alden Road will be completed during the day from 7am-3pm Monday- Friday


Byberry Road from Huntingdon Pike to Larch Road
updated 8/17/26:
This project has a tentative start date of 8/25/26
Crews will be working 9am-3:30pm Monday-Friday

Traffic control operations will be in place with flaggers maintaining a one-lane roadway. Please be advised local and emergency traffic will have access



Byberry Road from Creek Road to Paper Mill Road
updated 8/10/26
1 crew has installed 2,656 ft of gas main
The  following week the crew will begin working between Walsh Ln and Papermill Rd
Crews will be working 9:00 a.m. to 3:30 pm M-F
Traffic control operations are in place with flaggers maintaining a one-lane roadway.  Local and emergency traffic will have access


updated 5/4/26

PECO will be starting construction on Wednesday, May 27 for gas main replacement on Byberry Road (from Creek to Paper Mill).  Traffic control will be in place from 7 am to 3 pm.  Please allow extra time for travel through this area.

Project is expected to complete in Early September.